Do you offer CMM calibration near me?
On-site scheduling covers Pittsburgh and the surrounding Western Pennsylvania and Upper Ohio Valley region, including Butler, New Castle, Greensburg, Monroeville, Wheeling and Johnstown. Machines farther out are generally handled ship-in; ask when requesting a quotation.
What is the difference between calibration and verification?
Calibration establishes the relationship between a machine's indications and reference values with a stated uncertainty. Performance verification, the test usually sold as CMM calibration, confirms the machine still meets a stated specification.
Is the certificate accredited, and how do I check the scope?
Certificates are issued under the performing laboratory's scope of accreditation. The specific measurement, range and uncertainty should appear on that published scope, checked against the accreditation body's public directory before work is booked.
What does ISO 10360-2 actually test?
Length measurement error, E0 and E150, is verified at five calibrated lengths measured three times each in seven positions, 105 measurements total, against a stated maximum permissible error.
What happens if the machine fails as-found?
As-found data is recorded before any adjustment. Enough detail is reported to run a reverse-traceability impact assessment back to the last passing calibration.
What temperature does the room need to be?
ISO 1 fixes 20 degrees C as the dimensional reference temperature. For an acceptance test the manufacturer's specified environment applies; a reverification environment is whatever is recorded on that certificate.
Will this satisfy an IATF or AS9100 auditor?
Auditors under IATF 16949 clause 7.1.5.3 and AS9100 look for a laboratory's ISO/IEC 17025 accreditation and a traceability statement on the certificate, not a pass/fail slip with no data behind it.
What is an error map, and can it be updated on my controller?
The volumetric error-compensation map corrects for geometric error across the measuring volume. It can be updated during geometric adjustment on controllers that allow it; some OEM controllers lock that map.
Can an articulated arm be verified on the same certificate as a bridge machine?
No. Articulated arms are tested to ISO 10360-12, or the ASME B89.4.22 analogue where applicable to the arm and probe configuration, not as an extension of a bridge certificate.
What is a CMC and why does it matter to my tolerances?
Calibration and measurement capability is the smallest uncertainty a laboratory can claim within its scope. The scope CMC sets the floor; a reported uncertainty smaller than it counts as an audit finding, not a selling point.

Further Detail
Standards, traceability and equipment control are set out on the quality system page. Competence and authorization are covered on the our team page. Commercial terms are in the terms and conditions.
Question about a specific item?
Send the detail and it is answered against the method that would actually be used.